Capital Hill Reservoir Replacement Project Update
Our Capital Hill Reservoir Replacement Project has only been underway for a couple of months, but contractor Slayden Constructors has worked quickly to demolish Reservoir 1 and begin excavating the area for the new reservoir. Since excavation activities began in September, approximately 155 to 165 loads of material have been hauled, both by 13-yard and 20-yard trucks. Excavation will continue through the end of October, though the offsite hauling will...