.  
The Board Divisions Doing Business Water Quality Water Resources Conservation Jobs
Back to Engineering
LINE

2017 Water Distribution System Facility Plan
LINE
2016 Big Butte Springs & Robert A. Duff Water Treatment Plant Facility Plan
LINE
Development Fees/SDCs
LINE
Plan Submittal Application Packet
LINE
Ongoing Projects
LINE
Rogue Valley Water Supply Resiliency Program
LINE
Capital Hill Reservoir Replacement Project
LINE
Foothill Road Waterlines Relocation
LINE
Table Rock Road Pipeline Project
LINE
Regulations & Standards
LINE

200 S. Ivy St. - RM 177
Medford, OR 97501
Phone: 541-774-2428
Fax: 541-774-2555
Contact: Brian Runyen, P.E., Engineering Manager
Email: Brian.Runyen@medfo. . .
Hours: 8:00 AM - 5:00 PM

Medford Water Commission

Medford Water Commission - 541.774.2430
Table Rock Road Pipeline Project

Table Rock Road Table Rock Road Table Rock Road Table Rock Road Table Rock Road Project

Medford Water will install a new water pipeline along a section of Table Rock Road, to provide a seismically resilient connection from our water treatment plant to our distribution system and provide additional transmission capacity to support our growing community.



Project Description and Benefits
Robert A. Duff Water Treatment PlantThe Robert A. Duff Water Treatment Plant
 
  • Medford Water will install 18,000 feet of new 42" water transmission pipeline under and along Table Rock Road, from our Robert A. Duff Water Treatment Plant north of Kirtland Road to Vilas Road.
  • This project will not only provide additional water transmission capacity to support our growing community, but it will also provide a seismically resilient connection from our water treatment plant to the rest of our distribution system.
  • Contractor Pilot Rock Excavation will begin construction in the roadway in February 2024. We will provide more information as it becomes available.

Project Map  

Below is preliminary map of the area; to view and download a full-size version, click here. Please note that the active construction zone has a 35 mph posted speed limit; drive with caution.
 
Table Rock Road Project Map

Estimated Project Schedule
 
The anticipated construction schedule is February 2024 through May 2025. This schedule is subject to change; we will provide more information as it becomes available.
 
Project Updates/News   
 
Sign up at the bottom of the page to receive email updates; be sure to check your spam folders as these messages can sometimes get filtered.
 
Date   Update
     
March 2024   Construction activities within the Table Rock Rd. and Vilas Rd. intersection will begin the week of March 4th-8th, taking place at night to ease daytime traffic issues, and lasting approximately a couple of weeks. Following that, day work will continue from Vilas Rd. towards Kirtland Rd. and our water treatment plant. Please drive cautiously and be aware of changes to traffic patterns, the active construction zone has a 35 mph posted speed limit.
     
February 2024   Near the end of February, the contractor will begin excavation in various locations on Table Rock Road between our Robert A. Duff Water Treatment Plant north of Kirtland Road, to Vilas Road, to visually confirm the presence of utility lines. Nighttime work at the Vilas intersection was delayed slightly, but will begin in early March. Following that, day work will continue from Vilas towards Kirtland and our water treatment plant. The active construction zone will have a 35 mph posted speed limit; please drive with caution.
     
January 2024   Contractor Pilot Rock Excavation will begin construction in the roadway in February 2024, beginning at our water treatment plant. Near the end of February, construction work will also begin at the Vilas Road intersection; work in the intersection will take place at night to ease daytime traffic issues. We will minimize impacts as much as possible, but these activities will result in temporary lane closures and traffic delays as we carefully install this vital infrastructure. Please drive cautiously and be aware of changes to traffic patterns.
     
September 2023   Medford Water continues to receive materials for this project, and we are currently working with our partners at Jackson County and the City of Medford on required permitting and traffic control plans. 
     
July 2023   Design and permitting of this project is complete, and the construction contract was awarded by the Board of Water Commissioners to Pilot Rock Excavation on July 19, 2023. Medford Water pre-purchased the materials for this project in order to reduce costs and to better manage the long-lead times for pipeline components; the materials are currently being delivered to our storage location. 

The anticipated schedule is November 2023 through May 2025; we will provide more information on the schedule as it becomes available.

Project Documents  
 
Jackson County Project Press Release
  Jackson County's Project Press Release
 
Related Projects  
 
This project is part of the Rogue Valley Water Supply Resiliency Program, our multi-project effort to modernize and expand our water system for the next century, as well as protect it from emerging threats such as earthquakes, wildfires, and power outages. Learn more about the program here.

Contact
 
Lester McFall, Special Projects Manager
(541) 774-2675
Email

Media Contact
Yvette Finstad
(541) 774-2442
Email


 
   
 
Medford Water
Water for the Next Century.


printer friendly version Printer friendly version RSS RSS
Contact Us | Site Map | Terms of Use/Privacy | Subscribe
© Copyright 2009 Medford Water Commission - All Rights Reserved
Designed, Developed and Deployed by Project A, Inc

 

 

 

MY ACCOUNT BEINVENIDOS CONTACT US ABOUT MWC HOME